RIIO-T3 has started: delivering the digital and data commitments you were funded for

Ofgem's RIIO-3 Final Determinations landed in December 2025 and the price control period began on 1 April 2026. The business planning is finished. For the next five years the question that matters is whether the digital and data commitments inside those plans can be evidenced as delivered, by an organisation whose delivery record is now a regulatory exhibit.

The short answer

  • RIIO-3 covers 1 April 2026 to 31 March 2031, with £28.1bn of upfront funding approved inside a wider investment pipeline of around £90bn.
  • Digital and data commitments made in a business plan become reportable obligations for five years. Most were written by a team that has since moved on.
  • The common gap is that the plan committed to outcomes while the delivery organisation is instrumented to report on projects.
  • The work in year one is translating each commitment into a named owner, a measurable indicator and a reporting line that survives a change of programme director.

What the period actually locks in

Ofgem published Final Determinations for the electricity transmission, gas transmission and gas distribution sectors in December 2025, followed by a consultation on the licence modifications that give them effect, with the final licence decision issued in February 2026. That sequence matters for one practical reason: the numbers and the commitments stopped being negotiable at different moments, and a delivery plan written against the draft position can be materially out of step with the licence it now sits under.

For digital and data specifically, three things travel from the business plan into the control period and stay there:

  • Funded capability. The investment allowed for data platforms, asset information, digital twins and the systems supporting network capacity. Allowances are set; the spend has to land against the capability described.
  • Output commitments. What the network said the capability would let it do, expressed as consumer or system benefit rather than as a delivered system.
  • Reporting obligations. The annual submissions through which the regulator, and every stakeholder reading them, forms a view of whether the first two are converging.

The first is a finance problem and is usually well managed. The third is a regulatory affairs problem and is usually well staffed. The second is where the difficulty concentrates, because output commitments cut across the boundaries the delivery organisation is built around.

Why year one is where the drift starts

A business plan is written by a small, senior, cross-functional team over an intense period, and it is deliberately written in the language of outcomes because that is what a price control review rewards. Delivery then hands to a portfolio structured by system, by asset class and by capital programme, reporting on milestones, spend and schedule.

The translation between those two languages is rarely anybody's job. Nothing looks wrong for eighteen months: the programmes are green, the spend is on profile, the reporting is submitted on time. The gap only becomes visible at a mid-period review, when someone asks which commitment a particular green programme is discharging and the answer takes three weeks to assemble.

By then two years of evidence has been generated in a form that does not map to the obligations it was meant to evidence, and reconstructing it retrospectively is expensive and unconvincing.

The constraint

In most networks entering a new price control, the binding limit is traceability between a funded commitment and the delivery artefacts that evidence it. Capability, budget and reporting discipline are usually present. What is missing is a maintained line from each digital and data commitment through to the owner, the indicator and the specific programme discharging it, which is why the position can only be assembled by exception and never read off.

What good looks like in the first year

A commitment register that is a live object

One row per digital and data commitment from the accepted plan. Each row carries the commitment in the plan's own wording, the accountable director, the indicator that will show movement, the baseline as measured at 1 April 2026, the programmes contributing, and the annual submission it feeds. Built once and maintained monthly, it answers the mid-period question in an afternoon. Built retrospectively in year three, it is an archaeology exercise.

The baseline is the part most often skipped, and it is the part that cannot be recovered later. A commitment to improve data quality or asset information completeness needs its starting position recorded in the first months of the period. After that the network has changed and the original number is gone.

Indicators the organisation already produces

A commitment measured by an indicator invented for the purpose will be reported for two years and then quietly stop. Where an existing operational measure can carry the commitment, it survives reorganisations, because somebody needs it for their own reasons. Where no such measure exists, the honest conclusion is usually that the capability has no operational consumer yet, which is a finding worth surfacing early rather than at a review.

One owner per commitment, at director level

Commitments that cut across IT, asset management, operations and regulatory affairs tend to be owned by a forum. A forum can review, and it cannot be held to an outcome. Where four functions contribute, one director still has to be answerable for the commitment landing, with the others named as contributors.

The stakeholder dimension

Price control reporting is public, and it is read by parties with an interest in a gap between what was funded and what was delivered. That includes consumer bodies, other licensees, and the regulator preparing the evidence base for the next period. A network whose digital commitments are traceable and whose baselines were recorded is arguing from a position of fact. A network reconstructing its position under time pressure is arguing about interpretation, and it will carry that into the RIIO-4 process.

That is the strongest commercial reason to do this work in year one rather than year three. The cost of assembling traceability now is a few months of one team's attention. The cost of not having it is paid across the whole of the following price control review, in the credibility applied to every forward-looking claim the business plan makes.

Where to start

Read the accepted plan and extract every sentence that commits to a digital, data or information outcome, including the ones embedded in engineering and asset chapters rather than the digitalisation section. Most networks find between thirty and eighty. Then, for each, ask three questions: who is answerable, what number moves, and where is that number today. The commitments where all three answers exist are already safe. The ones where the third answer is missing are on a clock, because the baseline they need is expiring as the period runs.